Program mapping - Error message „There is no task defined for PLC

If the project has been switched to Full mode, all programs have to be mapped to tasks manually. Double click the PLC or right click the PLC and Open editor. In the Tasks tab, right click the editor window and select Add task.

Select the programs to be mapped in the dialog window.

In the left pane there are all programs available in a Solution, while the right pane contains programs which are already executed in the task. Clock OK to confirm changes. To save all changes to project, click the OK button in the red dialog.

 

Remember to switch back to the derived profile and upload the Solution to PLC to activate all changes.